PMP考试中净值管理计算公式 集合
Abb. FormulaDescriptionPV
BCWSPlanned Value or
Budget Cost of Work Scheduled
计划产出
The authorized budget assigned to the scheduled work to be accomplished for a schedule activity or work breakdown structure component. Also referred to as the budgeted cost of work scheduled (BCWS).P472)
The value of work performed expressed in terms of the approved budget assigned to that work for a schedule activity or work breakdown structure component. Also referred to as the budgeted cost of work performed (BCWP).(P464)
实际花费
Total costs actually incurred and recorded in accomplishing work performed during a given time period for a schedule activity or work breakdown structure component. Actual cost can sometimes be direct labor hours alone, direct costs alone, or all costs including indirect costs. Also referred to as the actual cost of work performed (ACWP). See also earned value management and earned value technique.(P457)
Are we under or over our budget?
Cost variance (%)How efficiently are we using our resources?
SVSchedule varianceAre we ahead or behind schedule?
Schedule variance (%)How efficiently are we using time?
Remaining budgetRemaining budgetIt is the ratio of “remaining work” to the “funds remaining.”(P482)
When you still feel you can complete it with the allocated budget.
If you think you cannot attain within current BAC then the forecasted value will be considered for the funding part of it.
修正后的预算
VACVariance at completion假设将按预算单价完成ETC工作。 按原定计划完成
所以用实际花费加上剩余工作