Project 1- Interconnections Program Office, Program Manager
(Company Name)
June 1997-present approx. 1500 hours
As Program Manager in Interconnections Program Office, provide project management expertise,
support, and standards to 10 project teams (list team names). Provide a centralized "status entity" for
project plans and status across three divisions.
Initiating Process 100 hours
oInitiation--For Measurements team, identified as project manager and given responsibility to
obtain necessary personnel to work on team.
Planning Process 600 hours
oScope Planning-For Measurements and XXX, developed and documented scope
statements.
oScope Definition-For Measurements and XXX, subdivided major deliverables.
oActivity Definition-For XXX, identified activities.
oActivity Sequencing-For all projects, identified and documented inter-activity dependencies.
oSchedule Development-For all projects, developed schedule with teams.
oResource Planning-Not applicable.
oCost Estimating-Not applicable.
oCost Budgeting-Not applicable.
oProject Plan Development - For all projects, standardized project plans into consistent
documents in both Microsoft Project and Word.
Executing Process 300 hours
oProject Plan Execution-Worked with teams to ensure project plan was performed.
oScope Verification-Not applicable.
oQuality Assurance-Not applicable.
oTeam Development-Work with teams as requested. Give recommendations to project leads.
Measurement team held kick-off meeting.
oInformation Distribution-Provide all teams the standardized information retrieval system
and information distribution system.
oSolicitation-Not applicable.
oSource Selection-Not applicable.
oContract Administration-Not applicable.